14,940,000,000.00 2016/05/01 2020/01/31 PROJECT IMPLEMENTATION Luzon III - Central Luzon

Project Description

This is a 30 km –four lane expressway from Tarlac City to Cabanatuan City, Nueva Ecija. It will reduce travel time between Tarlac City and Cabanatuan City from 70 minutes to 20 minutes. Moreover, it is expected to decongest traffic by about 48% passing thru Daang Maharlika.

Funding Source

Official Development Assistance (ODA)

MILESTONE

Progress: 16% - PROJECT DEVELOPMENT
100% Complete
Progress: 20% - PROJECT PROCUREMENT
100% Complete
Progress: 27.6% - PROJECT IMPLEMENTATION
58% Complete